Tiling was complete last week and painting should be finished on Wednesday, including the Moroka at the front, the weather isn't looking good for the rest of the week though so I will be surprised if they get the outside done. Flooring is scheduled to be installed next week. We should be getting a letter late this week / early next week with the final payment amount as well as PCI date!
Here are some pics from today:
Kitchen! |
Ensuite shower |
Ensuite vanity |
Bathroom |
Bathroom vanity |
Bathroom shower |
The lone Laundry tub! |